August 14, 2007

Power shutdown at McHenry Library on Saturday, September 8th

We have been notified by the campus that there will be a power shut down at McHenry Library on Saturday, September 8, between 7:00AM and 5:00 PM.

--Eric Baker, Library Operations

Date: Mon, 13 Aug 2007 15:34:22 -0700

UNIVERSITY OF CALIFORNIA, SANTA CRUZ

UTILITY SHUTDOWN
LOCATION(S): McHenry Library

UTILITY TO BE SHUT DOWN: Electric - Main Building Power

SCHEDULED DATE: 09/08/07 (Saturday)

SCHEDULED TIME: 07:00 AM - 05:00 PM

REASON: Main Breaker installation

REQUESTED BY: Bret Caton/Bob Roseberry

PHONE: 9-2407 / 423-1007 CELL: 212-0192

TODAY'S DATE: 08/13/07

PLEASE NOTIFY ALL UNITS AND/OR DEPARTMENTS IN YOUR BUILDING OR AREA THAT WILL BE AFFECTED BY THIS UTILITY SHUTDOWN. FOR ELECTRICAL SHUT DOWNS, BE SURE THAT ALL COMPUTER TERMINALS IN YOUR AREA ARE TURNED OFF BEFORE THE SCHEDULED TIME TO AVOID PROBLEMS. THANK YOU FOR YOUR COOPERATION.

FOR FURTHER QUESTIONS OR INFORMATION, PLEASE CONTACT THE "REQUESTER" OR THE PHYSICAL PLANT SERVICE CENTER WORK CONTROL DESK AT 459-4444.

Posted by lauramcc at August 14, 2007 03:27 PM