Next week, on Tuesday, August 7th, there will be construction work happening at the southwest corner of McHenry Library as they shotcrete retaining walls for the reading garden planters as part of the landscaping work now in progress. The pumping truck will be located near the ADA ramp at the southwest corner, just outside the Reference and Government Publications offices.
On the same day, work will begin on the new telecom room which will be located in Greg Careaga's former office in the Film & Music Center. The work on the new telecom room will continue through August 31st.
Next Thursday, August 9th, there will be an abatement taking place in Room 463 on the fourth floor. This will be followed by a 3-4 day demolition of the precast concrete panel, in preparation for the fourth floor opening to the addition that will be used during the collection and staff moves.
--Eric Baker, Head of Operations
Posted by lauramcc at August 3, 2007 01:47 PM