Consolidated Access Services desk in McHenry Library beginning August 7th

McHenry Library Access Services has spent the last year preparing for the consolidated service desk as presented in the building plans for the addition and renovation. This means McHenry Reserves, Interlibrary Loan, and Circulation services will all be available from a single service point beginning Monday, August 7th. Staff members are trained on all three services and they anticipate that patrons will benefit greatly from the ease of accessing all of their services at a single desk.

The primary contact number for McHenry Access Services will be 831-459-5185, which has been the main number for the Circulation Desk. However, there will likely be times during this transition when it will be more expedient to reach an Interlibrary Loan, Circulation, or McHenry Reserves expert. For those times, please feel free to use the following contact numbers:

Interlibrary Loan: (831) 459-2234
McHenry Reserves & Circulation: (831) 459-5344

July 25, 2006

Photos of McHenry addition foundation construction

They have begun laying the rebar for Mat #1 (the first pour of the foundation slab, on the east side of the addition). Utilities will be placed when the ironwork is completed. The concrete pour for Mat #1 should happen in mid-August.

update172506.jpg

update272506.jpg

update372506.jpg

update472506.jpg

Questions? Please contact us.

Biweekly construction schedule: July 25, 2006


Below is a link to a two-week projection of the construction schedule for McHenry Library. You will need Adobe Acrobat Reader to look at the file; to download a free version, visit the the Adobe site .

Download file

We will do our best to keep you informed prior to major construction impacts.

Questions? Please contact us.

July 18, 2006

Biweekly construction schedule: July 18, 2006


Below is a link to a two-week projection of the construction schedule for McHenry Library. You will need Adobe Acrobat Reader to look at the file; to download a free version, visit the the Adobe site .

Download file

We will do our best to keep you informed prior to major construction impacts.

Questions? Please contact us.

July 14, 2006

McHenry Library construction photos: July 14, 2006

Work continues on leveling and treating the building pad and chipping away at excess concrete on the columns along the southeast wall of the building. This is being done before they install more re-bar and begin constructing forms for a new concrete wall that will be poured.


construction5.jpg

construction4.jpg

construction2.jpg

construction1.jpg

construction3.jpg

July 11, 2006

Biweekly construction schedule: July 11, 2006

Below is a link to a two-week projection of the construction schedule for McHenry Library. You will need Adobe Acrobat Reader to look at the file; to download a free version, visit the the Adobe site .

Click here to download the two-week schedule.

We will do our best to keep you informed prior to major construction impacts.

Questions? Please contact us.