June 29, 2006

McHenry Library excavation update

Mass excavation has been completed and they have begun lime treatment of the soil which will be underneath the concrete pad. Beginning June 28th, they will start chipping excess concrete off the south columns to prepare for a new wall along the south side of the existing McHenry structure. This will take about nine days.

excavation1.jpg

excavation2.jpg

Questions? Please contact us.

June 22, 2006

Excavation photos of the south side of McHenry Library


Here are two photos taken in late June showing the progress of the excavation on the south side of McHenry Library.

south1.jpg

south2.jpg

Questions? Please contact us.

Biweekly construction schedule: June 20, 2006


Below is a link to a two-week projection of the construction schedule for McHenry Library. You will need Adobe Acrobat Reader to look at the file; to download a free version, visit the the Adobe site .

Click here to download the file

We will do our best to keep you informed prior to major construction impacts.

Questions? Please contact us.

June 02, 2006

Biweekly construction schedule: May 23, 2006


Below is a link to a two-week projection of the construction schedule for McHenry Library. You will need Adobe Acrobat Reader to look at the file; to download a free version, visit the the Adobe site .

Download file

We will do our best to keep you informed prior to major construction impacts.

Questions? Please contact us.